Dorchester Ave Service Relocation: Multi-Unit Service Upgrade, Chicago

Client
Will Power & Light LLC (electrical contractor)
Industry
Multi-unit residential (existing building, five utility meters)
Location
Chicago, IL (South Side); AHJ City of Chicago Department of Buildings; utility ComEd
Dates
June 2026 onward
Team Size
Services
Chicago permit drawing package (one-line, panel schedules, load calculations, site plan, floor plan)
ComEd Modification and Relocation application package
Fault-current and equipment-rating coordination with ComEd
Chicago Electrical Code and CECHA fitting compliance notes
Summary
The owner-electrician was moving the electrical service of a five-meter residential building from a rear basement location to a new entrance on the north side and upgrading it from an undersized 200A, 120/240V service. MHL prepared the permit drawings and the ComEd relocation package so the city permit and utility process could run in parallel.
Problem / Objective
Chicago requires its own electrical code, engineered drawings for plan review, and a separate ComEd application that cannot move until a permit number exists. The objective was one coordinated package that satisfied both reviewers and avoided correction rounds.
Process
Researched Chicago Department of Buildings and ComEd requirements and set a realistic schedule, since the owner’s target date could not be met by the approval pipeline.
Ran a video walkdown with the owner to capture existing panels, the north-side entrance location and conduit routing.
Sized the new service by load calculation using the Chicago diversification method.
Drew the package to Chicago Electrical Code (Title 14E) requirements: metallic conduit throughout, CECHA-approved fittings, and emergency lighting review for buildings of five or more units.
Requested available fault current from ComEd for equipment ratings; ComEd later issued transformer fault-duty data (100 kVA, 120/240V pad source).
Supported the owner through the ComEd site visit and permit filing.
Payoff / Results (Metrics)
City of Chicago electrical permit issued about two to three weeks after filing on 7/7/2026, with no comment cycle.
ComEd relocation application accepted for engineering review on an expedited basis, and the ComEd site engineer raised no questions on the specs or plans, per the owner.
Owner began construction under the permit in August 2026.
When this applies
A contractor or building owner in Chicago relocating or upgrading a multi-meter residential service and needing drawings that satisfy both the Department of Buildings and ComEd. Also relevant if you are unfamiliar with Chicago’s metallic-conduit and CECHA requirements or with the order of the permit and ComEd application steps.